My power bill went up again.
I live in Pennsylvania. Same house, same thermostat, same appliances. But the bill for September was 22% higher than September a year ago. I called my utility. The woman on the phone said capacity costs had gone up. She said it twice, like that would help.
I looked it up. And what I found is one of the strangest structural problems I have seen in years.
PJM Interconnection runs the largest electric grid in America. It serves 67 million people across 13 states and Washington, D.C. Every year, PJM holds an auction where power plants bid to keep the lights on. Utilities pay the clearing price. That cost flows into your bill.
For the 2024/2025 delivery year, the auction cleared at $28.92 per megawatt-day. One year later, it cleared at $269.92. The year after that, it hit the FERC-imposed ceiling: $329.17 per megawatt-day. It has stayed at the cap for three straight auctions.
That is an eleven-fold increase in two years.
But that is not the strange part.
The strange part is that the grid fell short. PJM's most recent auction, for the 2028/2029 delivery year, came up 6,831 megawatts below its reliability target. That is enough power for roughly five million homes. It was the second year in a row the grid missed. PJM has never done that before.
So the price is at the legal maximum. And there still is not enough power. The money is not solving the problem.
The reason is data centers.
PJM's independent market monitor found that data centers drove 63% of the price increase in the 2025/2026 auction. That added $9.3 billion in capacity costs that every ratepayer across 13 states now absorbs. Over the last four auctions, data-center-driven capacity charges totaled $29.4 billion — 46% of the $63.6 billion in total charges.
I have no idea when this reverses. Goldman Sachs estimates U.S. data center power demand will grow from 31 gigawatts in 2025 to 41 gigawatts this year to 66 gigawatts in 2027. EPRI projects data centers will consume 9% to 17% of all U.S. electricity by 2030, up from about 4% today.
The hyperscalers — Amazon, Microsoft, Google, Meta — committed more than $300 billion in combined capital spending for 2026 on AI infrastructure. That money builds the demand. But the generation to feed it does not exist yet. PJM's interconnection queue holds 811 new projects representing 220 gigawatts of proposed capacity. Most are years from producing a single watt.
And here is the part that keeps me up at night. NERC, the body that watches grid reliability across North America, said in January that 13 of its 23 assessment areas face elevated or high resource adequacy risk over the next five years. Its director of reliability put it plainly: infrastructure is not being built fast enough to keep up with rising demand.
So demand is growing at the fastest pace in decades. Supply is short. Prices have hit their legal ceiling. And the companies that own the power plants — the ones everybody assumed would benefit — are losing money for shareholders. Constellation Energy, which runs the largest nuclear fleet in the country, is down 28% this year. Vistra, another major generator, is down about 15%.
The grid needs more power than it can buy. The people building the demand are spending hundreds of billions. The people who make the power are watching their stock prices fall. And the people who pay the electric bill — 67 million of them — are absorbing the cost of all of it.
That is this week's story.
|